Crafts Avenue Sewer Work Delayed
We have not been able to secure an excavation permit from the City of Lebanon to start the sewer work on Crafts Avenue. Consequently, we do not have time to complete the work this fall as originally hoped for prior to the deadline for street work found in the municipal ordinance. I am really sorry we will have to now delay this work to be done in conjunction with the construction of the first building at River Park.
All of the pre-construction surveying and stockpiling of materials on the River Park site has been completed. This should reduce the time necessary to complete the work once the excavation permit is granted.
Our attorney continues to exchange information with the City’s attorney and I am hopeful all outstanding issues can be resolved by the end of next week. I will update the blog when we have more information.